Benton PUD prepares an annual Load Forecast to estimate its future customer count and energy sales for at least the next ten years. The Load Forecast is a key input into Benton PUD's power supply planning, budgeting, monthly revenue projections, rate analysis, and capital improvement plans.
Benton PUD’s recent load forecasts:
- 2026 Load Forecast – approved by Resolution No. 2726 on 5/26/2026
- Presentation – 5/26/2026
- Presentation – 5/26/2026
- 2025 Load Forecast – approved by Resolution No. 2694 on 5/13/2025
- Presentation – 5/13/2025
- 2024 Load Forecast – approved by Resolution No. 2673 on 5/14/2024
- 2023 Load Forecast – approved by Resolution No. 2639 on 6/13/2023
- 2022 Load Forecast – approved by Resolution No. 2600 on 4/26/2022
Benton PUD prepares a Conservation Potential Assessment (CPA) every two years. The Washington State Energy Independence Act requires electric utilities serving 25,000 or more customers to pursue all conservation that is cost-effective, reliable, and feasible. By January 1 of each even-numbered year, a utility must identify its achievable cost-effective conservation potential for the upcoming ten years and a biennial target.
Benton PUD’s recent CPA’s:
- 2025 CPA – approved by Resolution No. 2700 on 8/12/2025
- 2023 Amended CPA – approved by Resolution No. 2670 on 4/23/2024
2025 Conservation Potential Assessment
Benton PUD prepares a Demand Response Potential Assessment (DRPA) every two years to support the Clean Energy Transformation Act (CETA) requirement to assess the amount of demand response resource that is cost-effective, reliable, and feasible.
Benton PUD’s recent DRPA’s and demand response presentations:
- 2025 DRPA – 6/20/2025
- 2023 DRPA – 1/9/2024
- 2022 Commission Strategic Session – 10/11/2022
- 2021 DRPA – 11/9/2021
- 2019 Commission Strategic Session – 10/8/2019

Modeling Demand Response Potential
Benton PUD prepares a resource plan every two years in accordance with Revised Code of Washington (RCW) 19.280. As described within RCW 19.280.010, “It is the intent of the legislature to encourage the development of new safe, clean, and reliable energy resources to meet demand in Washington for affordable and reliable electricity. To achieve this end, the legislature finds it essential that electric utilities in Washington develop comprehensive resource plans that explain the mix of generation and demand-side resources they plan to use to meet their customers' electricity needs in both the short term and the long term.”
Effective October 1, 2023, Benton PUD became a full requirements customer, as defined by RCW 19.280.020—meaning an electric utility that relies on Bonneville Power Administration for all power needed to supply its total load requirement other than that served by non-dispatchable generating resources totaling no more than six megawatts or renewable resources.
Benton PUD’s recent resource plans:
- 2026 Resource Plan
- Final Plan – approved by Resolution No. 2729 on 7/14/2026
- Plan Development & Public Process
- 2024 Resource Plan
- Final Plan – approved by Resolution No. 2681 on 8/27/2024
- Commerce Cover Sheet Submittal (Excel File)
- Plan Development & Public Process
- Public Hearing - 8/27/2024
- Draft Plan - 8/13/2024
- Introduction - Commission Presentation, 6/25/2024
- Final Plan – approved by Resolution No. 2681 on 8/27/2024
2024 Resource Plan
The Clean Energy Transformation Act (CETA), Revised Code of Washington (RCW) 19.405, requires utilities to be greenhouse gas neutral by 2030 and carbon free by 2045. Benton PUD’s electricity supply is already over 80% carbon free primarily due to hydroelectric and nuclear power. CETA requires by January 1, 2022, and every four years thereafter, consumer owned utilities to develop and submit to the Department of Commerce a four-year Clean Energy Implementation Plan (CEIP) with specific targets for energy efficiency, demand response, and renewable energy as well as actions to support an equitable transition to the state's clean energy goals.
Benton PUD’s recent CEIP’s:
- 2026-2029 CEIP
- Final Plan – approved by Resolution No. 2710 on 10/28/2025
- Commerce Template Submittal (Excel File)
- CEIP Development Webpage – Plan Development & Public Process
- Final Plan – approved by Resolution No. 2710 on 10/28/2025
- 2022-2025 CEIP
- Final Plan – approved by Resolution No. 2585 on 11/9/2021
- Commerce Template Submittal (Excel File)
- Draft Plan – 10/12/2021
- Public Meeting #2, 8/24/2021
- Public Meeting #1, 7/27/2021
- Final Plan – approved by Resolution No. 2585 on 11/9/2021